Foster Wheeler Corp said itsenergy subsidiary signed a 90 mln dlr contract to design,
engineer and construct two 550 mega-watt steam generators to be
installed at the new Taichung Fossil Power project of Taiwan
Power Co, Taiwan.
    The contract also includes an option for two additional 550
mega-watt units for the same site, the company said.
    Taiwan Power Co's long range plans call for the
installation of a total of eight units at the station.
    Commercial operation of the two units is scheduled for June
and December 1991, respectively, the company added.